MT431 E-Business Project & Data Engineering: Meeting 13

UR Berdampak Diktisaintek Berdampak raharja.ac.id ↗

Slide · Mata kuliah MT431 · 2026

View the original document All documents

Overview

Executive summary

Meeting 13 covers planning and managing e-business development projects. The material traces the project lifecycle from initiation and feasibility through planning and architecture to execution and go-live. Agile or Scrum practices are explained through the product backlog and user stories, sprint planning, daily standups and reviews, and retrospectives. The work breakdown structure (WBS) is divided into frontend, backend services, data engineering pipeline, and QA and security audit. Triple-constraint control uses Earned Value Management with SPI and CPI targets of at least 1.0, while stakeholder management and a change control board address scope creep.

This summary is based on the text of the original document. For official citation, refer to the original file below.

Key points

What to know

  • Three project lifecycle phases: initiation and feasibility (project charter, feasibility study, and KPIs), planning and architecture (WBS, Agile sprint estimates, data architecture design, and budget), and execution and go-live (development, integration, UAT, deployment, and handover).
  • Agile or Scrum components: product backlog and user stories, sprint planning with 2- to 4-week cycles, daily standups and reviews, and sprint retrospectives.
  • WBS for an e-business project: 1.0 frontend development, 2.0 backend services, 3.0 data engineering pipeline (ETL or ELT, data lakehouse, and ERP and CRM integration), and 4.0 QA and security audit (automated testing, load testing, VAPT, and UAT).
  • Triple-constraint control with Earned Value Management keeps Schedule Performance Index (SPI) and Cost Performance Index (CPI) at a minimum of 1.0.
  • Stakeholder management uses a power/interest grid; the risk register records technical risks, vendor delays, and contingency plans.
  • A change control board prevents scope creep.
  • The slides recommend Agile or Scrum for e-commerce applications and distributed data platforms because it adapts to change and releases an MVP faster than waterfall.

Document content

Content by chapter

Full text in Indonesian.

Full text in Indonesian

Siklus hidup proyek e-business

  1. Inisiasi dan feasibility: penyusunan project charter, studi kelayakan bisnis, dan penetapan KPI utama proyek.
  2. Planning dan architecture: perancangan WBS, estimasi sprint Agile, desain arsitektur data, dan anggaran biaya.
  3. Execution dan go-live: pengembangan sistem, integrasi data, UAT, deployment, dan handover pasca-launch.

Penerapan Agile atau Scrum

  • Product backlog dan user stories: daftar fitur berprioritas tinggi yang diterjemahkan dari kebutuhan bisnis ke user story teknis.
  • Sprint planning dan iterasi: pengerjaan fitur bertahap selama 2 sampai 4 minggu dengan target rilis inkremental.
  • Daily standup dan review: koordinasi singkat harian dan demonstrasi fitur kepada pemangku kepentingan.
  • Sprint retrospective: evaluasi proses tim untuk perbaikan pada sprint berikutnya.

Work breakdown structure

Paket kerjaNamaCakupan
WBS 1.0Frontend developmentDesain UI/UX, katalog produk, modul keranjang belanja, dan antarmuka mobile responsive
WBS 2.0Backend servicesPengembangan API microservices, payment gateway, authentication, dan engine pesanan
WBS 3.0Data engineering pipelinePipeline ETL/ELT, penyusunan data lakehouse, dan integrasi sistem ERP dan CRM
WBS 4.0QA dan security auditPengujian otomatis, load testing, uji penetrasi (VAPT), dan UAT

Pengendalian triple constraint

Earned Value Management (EVM) dipakai untuk menjaga Schedule Performance Index (SPI) dan Cost Performance Index (CPI) pada nilai minimal 1,0. Dengan begitu proyek e-business selesai tepat waktu dan sesuai alokasi anggaran tanpa mengorbankan kualitas.

Manajemen stakeholder dan risiko

  1. Stakeholder mapping: matriks kekuasaan dan minat (power/interest grid) untuk menyusun strategi komunikasi tim.
  2. Risk register: dokumentasi risiko teknis, keterlambatan vendor, dan rencana penanggulangan (contingency).
  3. Change management: prosedur kontrol perubahan melalui change control board untuk mencegah scope creep.

Agile dan waterfall

KriteriaAgile/Scrum (rekomendasi digital)Traditional waterfall
Fleksibilitas perubahan fiturTinggi, adaptif di setiap akhir sprintRendah, perubahan mahal setelah fase desain
Kecepatan rilisCepat, rilis MVP dalam hitungan mingguLama, rilis dilakukan penuh di akhir siklus
Keterlibatan klien atau bisnisKontinu di setiap sprint reviewDominan di awal dan akhir pengujian
Kesesuaian jenis proyekAplikasi e-commerce dan platform data terdistribusiPengadaan infrastruktur fisik atau proyek statis

Dipakai di mana

Pertemuan 13 membahas perencanaan dan manajemen proyek e-business. Sub-CPMK12 pada RPS: Menyusun perencanaan proyek E-Business dan data engineering yang meliputi ruang lingkup, tujuan, tahapan pekerjaan, jadwal, sumber daya, dan pembagian tugas. Mata kuliah MT431 memetakan CPMK013 (Mampu merekayasa solusi platform e-business terintegrasi.), CPMK024 (Mampu mengintegrasikan model analitik prediktif.), CPMK037, dan CPMK043 pada peta CPL kurikulum. Halaman terkait:

Source

Original document

A preview of this file cannot be shown on the site yet because its access is still restricted. The summary and contents above were prepared from the original file.

Open the original document ↗