MT423 IT Project & Risk Management: Meeting 15

UR Berdampak Diktisaintek Berdampak raharja.ac.id ↗

Slide · Mata kuliah MT423 · 2026

View the original document All documents

Overview

Executive summary

Meeting 15 brings the course together in a case study on drafting an IT project plan and its risks. IT projects are temporary, produce unique results, and carry uncertainty, so a good plan and risk management must go together. The plan is built from scope, WBS, schedule, cost, resources, and supporting plans. Risks are identified from each plan component, and mitigation strategies (avoid, transfer, mitigate, or accept) are carried into the WBS, schedule, and budget. The meeting assesses plans and risks through case studies, discussion, and presentation.

This summary is based on the text of the original document. For official citation, refer to the original file below.

Key points

What to know

  • IT projects are temporary, produce unique results, and carry uncertainty.
  • The project plan covers scope, WBS, schedule, cost, resources, and supporting quality, communication, and risk plans.
  • Risks are identified from each plan component.
  • Mitigation must appear as real tasks in the WBS, schedule, and budget.
  • The output is a project management plan with approved scope, schedule, and cost baselines.

Document content

Content by chapter

Full text in Indonesian.

Full text in Indonesian

Kemampuan akhir yang diharapkan

  • Menjelaskan karakteristik proyek TI dan hubungan antara proyek dengan risiko.
  • Menyusun rencana proyek TI (lingkup, WBS, jadwal, biaya, dan sumber daya).
  • Mengidentifikasi risiko proyek TI dan mencatatnya dalam register risiko.
  • Menentukan strategi mitigasi risiko dan mengintegrasikannya ke dalam rencana proyek.

Proyek TI dan risikonya

  • Ciri proyek TI: sementara (ada awal dan akhir), menghasilkan sesuatu yang unik, memiliki kendala lingkup, jadwal, biaya, dan kualitas, serta teknologi yang cepat berubah.
  • Mengapa berisiko: kebutuhan sering berubah, estimasi sulit pada pekerjaan kreatif, integrasi dengan sistem lama, serta ketergantungan pada vendor dan SDM kunci.

Penyusunan rencana proyek

  1. Lingkup: tujuan, deliverable, dan batasan.
  2. WBS: pecah pekerjaan menjadi paket kerja.
  3. Jadwal: urutan, durasi, dan milestone.
  4. Biaya: estimasi dan anggaran.
  5. Sumber daya: peran, tim, dan perangkat.
  6. Rencana pendukung: kualitas, komunikasi, dan risiko.

Hasilnya adalah rencana manajemen proyek. Baseline lingkup, jadwal, dan biaya dijadikan acuan pengendalian, lalu ditinjau dan disetujui sponsor serta pemangku kepentingan.

Identifikasi risiko dan strategi mitigasi

Komponen rencanaContoh risiko
LingkupKebutuhan pengguna berubah atau tidak jelas
JadwalEstimasi terlalu optimis, ketergantungan antar tugas
BiayaLisensi dan infrastruktur melebihi perkiraan
Sumber dayaDeveloper kunci keluar, keahlian tim kurang
Teknologi dan vendorIntegrasi API gagal, vendor terlambat, kebocoran data
  • Teknik identifikasi: brainstorming dan workshop, wawancara pakar, analisis SWOT, checklist dan lessons learned, serta tinjauan asumsi dan WBS.
  • Hindari: mengubah rencana agar risiko tidak terjadi, misalnya menghapus fitur berisiko tinggi.
  • Transfer: memindahkan dampak ke pihak ketiga, misalnya asuransi siber atau kontrak vendor dengan penalti.
  • Mitigasi: mengurangi probabilitas atau dampak, misalnya prototipe dini, uji keamanan, dan backup.
  • Terima: mengakui risiko, dengan cadangan bila perlu, misalnya untuk risiko rendah dan cadangan waktu.

Integrasi mitigasi ke rencana proyek

RisikoStrategiTindakan mitigasiDampak pada rencana
Integrasi API gagalMitigasiPrototipe integrasi di sprint 1Tambah tugas di jadwal
Kebutuhan berubahMitigasiProsedur kendali perubahan, review rutinCadangan waktu dan biaya
Developer kunci keluarMitigasiDokumentasi, pair programmingAlokasi waktu transfer pengetahuan
Kebocoran dataMitigasi + transferEnkripsi, pentest, asuransi siberAnggaran keamanan

Data pada tabel bersifat ilustrasi. Tindakan mitigasi menjadi tugas nyata di WBS, jadwal, dan anggaran.

Source

Original document

A preview of this file cannot be shown on the site yet because its access is still restricted. The summary and contents above were prepared from the original file.

Open the original document ↗

Document Preview

Smart Search MTI Universitas Raharja

Recommended: