Overview

Executive summary

Meeting 14 covers monitoring, controlling, and evaluation of IT projects. Monitoring collects and reports performance data, while controlling compares it with the baseline and takes corrective or preventive action when deviations occur. Scope changes are managed through logging, impact assessment, and approval by a Change Control Board, and baselines change only through this procedure. Cost and schedule performance is evaluated with Earned Value Management, using CV, SV, CPI, SPI, and EAC. The meeting closes with post-project review and recording of lessons learned.

This summary is based on the text of the original document. For official citation, refer to the original file below.

Key points

What to know

  • Monitoring measures and reports; controlling compares against the baseline and acts.
  • Change requests are logged, assessed, and approved or rejected by the Change Control Board.
  • Cost and schedule variance, together with the cost and schedule performance indices, show whether a project is over budget or behind schedule.
  • Estimate at Completion (EAC) projects the project's final cost if current cost performance continues.
  • The final evaluation records lessons learned for future projects.

Document content

Content by chapter

Full text in Indonesian.

Full text in Indonesian

Kemampuan akhir yang diharapkan

  • Menjelaskan tujuan dan proses monitoring serta pengendalian proyek TI.
  • Menetapkan indikator dan menyusun laporan kinerja untuk memantau kemajuan proyek.
  • Menerapkan pengendalian perubahan dan tindakan korektif ketika terjadi penyimpangan.
  • Mengevaluasi kinerja biaya dan jadwal dengan Earned Value Management dan merumuskan lessons learned.

Monitoring dan controlling

  1. Rencanakan baseline.
  2. Ukur kinerja aktual.
  3. Bandingkan dan analisis varians.
  4. Ambil tindakan.
  5. Perbarui rencana dan ulangi.
  • Laporan kinerja memuat status hijau, kuning, atau merah; pencapaian periode ini; rencana periode berikutnya; serta isu, risiko, dan keputusan yang dibutuhkan.
  • Pengendalian perubahan: permintaan perubahan dicatat dan dinilai, Change Control Board menyetujui atau menolak, dan perubahan yang disetujui memperbarui baseline.

Jenis tindakan

  • Korektif: mengembalikan kinerja ke rencana.
  • Preventif: mencegah penyimpangan di masa depan.
  • Perbaikan cacat: memperbaiki hasil yang tidak sesuai.
  • Contoh: menambah sumber daya, mengurangi lingkup, atau mempercepat jadwal melalui crashing dan fast tracking.

Evaluasi kinerja: Earned Value Management

UkuranRumusInterpretasi
Cost Variance (CV)EV - ACNegatif: biaya melebihi anggaran
Schedule Variance (SV)EV - PVNegatif: terlambat dari jadwal
Cost Performance Index (CPI)EV / ACKurang dari 1: boros; lebih dari 1: hemat
Schedule Performance Index (SPI)EV / PVKurang dari 1: lambat; lebih dari 1: lebih cepat
Estimate at Completion (EAC)BAC / CPIPerkiraan total biaya akhir

BAC adalah anggaran total pada saat selesai. Rumus EAC berlaku bila kinerja biaya saat ini berlanjut.

Contoh di materi: pada minggu ke-8, proyek dengan nilai PV, EV, dan AC tertentu menghasilkan CPI 0,91 dan SPI 0,80, sehingga proyek dinilai boros dan terlambat. Nilai uang pada contoh tidak ditampilkan di halaman ini. Tindakan yang disebut: tinjau lingkup, tambah sumber daya, atau kurangi fitur.

Source

Original document

A preview of this file cannot be shown on the site yet because its access is still restricted. The summary and contents above were prepared from the original file.

Open the original document ↗

Document Preview

Smart Search MTI Universitas Raharja

Recommended: