Overview

Executive summary

Meeting 12 covers identification and analysis of IT project risks. Identification is repeated using techniques such as brainstorming, Delphi, expert interviews, SWOT, and fishbone analysis, and recorded in a risk register. Risks are written as cause, risk, and impact so they can be assessed. Qualitative analysis sets priorities through probability times impact on a P x D matrix, while quantitative analysis gives numerical values such as expected monetary value (EMV). The material stresses that quantitative analysis is used for high-priority risks.

This summary is based on the text of the original document. For official citation, refer to the original file below.

Key points

What to know

  • Risk identification is repeated because new risks can appear during the project.
  • Risk statements follow the form: CAUSE, which may lead to RISK, which would affect IMPACT.
  • Qualitative analysis comes first; quantitative analysis is used for high-priority risks.
  • A risk score combines likelihood and impact and is grouped into low, medium, and high.
  • Expected Monetary Value (EMV) estimates the monetary value of a risk from its likelihood and impact; the total helps size the project's contingency reserve.

Document content

Content by chapter

Full text in Indonesian.

Full text in Indonesian

Kemampuan akhir yang diharapkan

  • Mengidentifikasi risiko proyek TI dengan teknik yang sesuai dan mencatatnya dalam register risiko.
  • Menganalisis risiko secara kualitatif dan kuantitatif berdasarkan probabilitas dan dampak.
  • Menentukan tingkat risiko menggunakan matriks probabilitas-dampak.
  • Memprioritaskan risiko proyek TI sebagai dasar perencanaan respons risiko.

Identifikasi risiko

  • Teknik: brainstorming dan workshop, teknik Delphi, wawancara pakar, analisis SWOT, analisis akar masalah (fishbone), serta analisis asumsi dan checklist.
  • Sumber informasi: dokumen proyek (charter, lingkup, jadwal), lessons learned proyek sebelumnya, register stakeholder, serta kontrak dan perjanjian vendor.
  • Register risiko memuat ID dan deskripsi risiko, penyebab dan dampak, kategori (RBS), pemilik risiko, dan respons awal yang mungkin.
PenyebabRisikoDampak
Tim belum pernah memakai framework baruKualitas kode rendah dan banyak bugJadwal mundur dan rework
Server produksi belum diuji bebanSistem lambat saat banyak penggunaPengguna kecewa, kinerja tidak tercapai
Vendor hanya satu pemasokVendor terlambat mengirim modulIntegrasi terlambat, biaya naik

Pernyataan seperti 'proyek ini sulit' terlalu umum dan tidak dapat dinilai; pernyataan risiko harus spesifik.

Analisis risiko

  • Analisis kualitatif: menilai probabilitas dan dampak secara subjektif dengan skala; cepat, murah, dan menghasilkan peringkat prioritas. Alat: matriks P-D dan Risk Breakdown Structure.
  • Analisis kuantitatif: menghitung dampak secara numerik, misalnya dengan EMV, analisis sensitivitas (tornado), simulasi Monte Carlo, dan pohon keputusan.

Penilaian tingkat risiko: matriks P x D

  • Skor risiko ditentukan dari peluang dan dampak.
  • Hijau (1-5): rendah, pantau.
  • Kuning (6-14): sedang, rencanakan respons.
  • Merah (15-25): tinggi, tindakan segera.
  • Contoh: vendor terlambat dengan P = 4 dan D = 4 memberi skor 16 (tinggi). Developer sakit dengan P = 3 dan D = 2 memberi skor 6 (sedang).

Materi juga membahas Expected Monetary Value (EMV), yaitu perkiraan nilai uang dari setiap risiko berdasarkan peluang dan dampaknya. Total EMV dipakai untuk menentukan besar cadangan dana darurat proyek.

Source

Original document

A preview of this file cannot be shown on the site yet because its access is still restricted. The summary and contents above were prepared from the original file.

Open the original document ↗

Document Preview

Smart Search MTI Universitas Raharja

Recommended: