Kemampuan akhir mahasiswa
- Menjelaskan konsep manajemen biaya proyek TI.
- Menerapkan teknik estimasi biaya proyek.
- Menyusun anggaran dan cost baseline proyek.
- Mengendalikan biaya proyek dengan analisis nilai yang diperoleh (earned value).
Official documents
raharja.ac.id ↗
Bahan ajar · Mata kuliah MT423 · 2026
Overview
Meeting 6 covers cost management and budgeting for IT projects, including cost estimation, budget preparation, and cost control. Estimates use analogous or bottom-up methods, distinguishing direct and indirect costs, and fixed and variable costs. The budget aggregates work package costs into a cost baseline, separates contingency reserve from management reserve, and is approved by the sponsor. Cost control uses PV, EV, and AC to calculate cost variance and cost performance, where a CPI below 1 indicates overspending.
This summary is based on the text of the original document. For official citation, refer to the original file below.
Key points
Document content
Full text in Indonesian.
Full text in Indonesian
| Istilah | Arti |
|---|---|
| PV (Planned Value) | Nilai rencana |
| EV (Earned Value) | Nilai pekerjaan yang sudah diperoleh |
| AC (Actual Cost) | Biaya aktual |
| Cost variance (CV) | Nilai negatif berarti biaya melebihi nilai pekerjaan |
| Cost performance index (CPI) | Di bawah 1 berarti proyek boros |
Mata kuliah MT423 memetakan CPMK036 (Mampu menyusun mitigasi risiko implementasi sistem.) dan CPMK042 (Mampu mengelola siklus proyek TIK terpadu.) pada peta CPL kurikulum. Halaman terkait: